logo
September 17, 2018

Re: 2018 Street Improvements Project

Streets: East Winchester Road and Second Avenue

Weather permitting, final asphalt surface placement is scheduled for tomorrow Tuesday September 18, 2018. Preparatory work will take place today.  Prior to the start of paving, the contractor will be placing prime coat (oil) in preparation for asphalt placement. 

WATCH FOR “FRESH OIL” SIGNS. These will typically be placed just outside of the construction zone at least 24 hours before the application of road oil.

The Village of Libertyville requests that all vehicles are off the streets listed above from 7am to 5pm.

For any problems which may develop after hours, please call the Police non-emergency number (847) 362-8310, and they will contact the proper personnel for follow-up. Thank you again for your cooperation.  As always, your patience and cooperation throughout this process is greatly appreciated. 

Sincerely, 
Fred Chung
Senior Project Engineer
Powered by CivicSend - A product of CivicPlus