Re:   2018 Street Improvements Project
 
Streets: Second Avenue
 
Dear Resident:
 
The next phase of the project is scheduled to begin on Monday, August 27. The contractor will be grinding the asphalt off of the street. After the grinding, concrete patching of the roadway base will be identified and marked for removal. The schedule will be as follows (weather permitting):
 
Tuesday August 28, 2018: Grind asphalt surface and saw cut roadway patches.
Wednesday August 29, 2018: Remove concrete roadway patches on the east half of Second Avenue only.
 
You will have access to your driveway unless otherwise notified. Driveway closure notices will be distributed to residents on the east side of Second Ave.
 
We have made the Police Department aware that overnight parking will be present.  Please note however, that vehicles lacking a current Village vehicle sticker are subject to being ticketed.
 
For any questions regarding the construction, please call the Engineering Division Office at (847) 918-2100 or for any problems which may develop after hours, please call the Police non-emergency number (847) 362-8310, and they will contact the proper personnel for follow-up. 
 
Thank you again for your cooperation.
 
Sincerely,
 
Fred Chung
Senior Project Engineer